Fiscal Year 2014/15

The following list identifies areas on campus that will undergo upgrades of telecommunications cabling and installation of additional wireless access points (WAPs) beginning the week of January 27, 2014. 

This is a multi-year project. Learn about progress made in other years:

Fiscal Year 2013/14

Fiscal Year 2015/16 

*Areas with an asterisk received updated WAPs (hardware) where WAPs already existed.

(Tip:  to find a specific building, in most browsers you can use the “find” feature by simultaneously pressing Ctrl+F and typing in the building name. You can also use the table column headings to sort in alphabetical or numerical order.)

Building

Area

Start Date

Status

Liberal Arts 5

1st floor

Jul-14

completed 8/5/14

Liberal Arts 5

2nd floor

7/31/2014

completed 8/22/14

Liberal Arts 5

3rd floor

7/31/2014

completed 8/22/14

ED1

room 40 and 41

8/21/2014

completed 8/22/14*

ED2

room 158

8/22/2014

completed 8/22/14*

Psychology

1st and 2nd Floors

9/2/2014

completed 9/5/15*

MLSC

Entire Building

9/8/2014

completed 9/12/14*

CBA

Entire Building

9/22/2014

completed 9/24/14*

HSCI

Entire Building

9/24/2014

completed 10/6/14*

LA1

2nd and 3rd floors

10/1/2014

completed 10/3/14*

ECS

Entire Building

10/7/2014

completed 10/27/14*

Academic Services

Entire Building

10/10/2014

completed 10/22/14*

Library

0, 1st, 2nd. And 3rd

10/13/2014

completed 10/17/14*

HHS1 2 classrooms

rm 104 / rm 201

10/24/2014

completed 10/24/14*

CPAC House

Main Theater

10/24/2014

completed 10/24/14*

Nursing

rm 25, 22

10/29/2014

completed 10/29/14*

Fine Arts 1

most areas

10/29/2014

completed 10/30/14*

Fine Arts 2

most areas

10/29/2014

completed 11/26/14*

Fine Arts 3

most areas

10/29/2014

completed 11/26/14*

Fine Arts 4

classrooms

11/10/2014

completed 11/26/14*

Engineering 2

1st and 2nd Floors

10/31/2014

completed 4/10/2015

Engineering 2

3rd floor

11/15/2014

completed Dec., 2014

Vivian Engineering Center

1st floor ext rooms

12/15/2014

pending final testing

Liberal Arts 2, 3, and 4

ALL areas

 

completed Jan., 2015

HHS1

Entire Building

2/3/2015

completed 2/13/15

HHS2

external offices

2/3/2015

completed 2/12/15

Faculty Office 2

1st floor

2/10/2015

completed 2/18/2015

Faculty Office 2

2nd floor

2/11/2015

completed 2/18/2015

Faculty Office 3

Lower Level

2/18/2015

completed 2/19/2015

Liberal Arts 1

2nd floor

2/19/2015

completed 6/10/2015

Liberal Arts 1

3rd floor

2/19/2015

completed 6/12/2015

Fine Arts 1

1st floor

2/23/2015

completed 3/17/2015

Fine Arts 1

2nd floor

2/23/2015

completed 3/17/2015

Academic Services

3rd floor

3/10/2015

completed 3/20/2015

Multi Media Center

1st and 2nd Floors

3/11/2015

completed 4/17/2015

Pyramid

Fitness Complex

3/18/2015

completed 3/26/2015

Fine Arts 4

3rd floor

3/24/2015

completed 4/10/2015

Social Sciences / Public Affairs

3rd and 2nd floors

4/7/2015

completed 4/16/2015

Liberal Arts Building

2nd floor

4/16/2015

completed 5/1/2015

Liberal Arts Building

3rd floor

4/16/2015

completed 5/1/2015

CPAC

Lobby

4/20/2015

completed 4/23/2015

Liberal Arts Building

1st floor

4/24/2015

completed 4/29/2015

Faculty Office 5

1st floor

4/29/2015

completed 5/22/2015

Faculty Office 5

2nd floor

5/1/2015

completed 5/22/2015

University Music Center "A"

Side A

5/4/2015

completed 5/20/2015

Design

ALL areas

5/22/2015

completed 6/12/2015

Social Sciences / Public Affairs

1st floor

6/11/2015

completed 6/19/2015

Design

ALL areas

6/19/2015

completed 7/2/2015

*Areas with an asterisk received updated WAPs (hardware) where WAPs already existed. 

Read the Annual Report for Fiscal Year 2014/15 with graphical representations of the improvements.
 

Learn about progress on Computer Lab improvements funded by the Student Excellence Fund (SEF).